Road surveys to begin as part of University Masterplan

18 April 2018

Investigations will temporarily affect access to highways in the Adelphi Quarter

The second phase of a series of road and pavement investigations is due to take place in the Adelphi Quarter of Preston in preparation for the construction of the next phase of the University of Central Lancashire’s (UCLan) Masterplan project.

On 11 January 2018, planning approval was granted to UCLan for the £57 million Student Centre and Civic Square project. As a result, a number of inspection trenches will be excavated in and around the Adelphi roundabout and connecting pavements and roads between February and May.

The objective is to establish the precise locations of utilities, distribution networks and other underground features.

The investigations are taking place in two phases. Phase one, which affected access to pedestrian pavements only, has now been completed.

Phase two will begin on Sunday, 22 April, and will continue every Sunday for the next three weeks. The roads affected include sections of Corporation Street, Friargate, Moor Lane, Walker Street and Fylde Road.

Full road closures will be in place on Sundays, with diversions in place to guide vehicles around the works.

Michael Ahern, UCLan’s Chief Operating Officer, said: “Works are being carried out on Sundays when the lowest volume of traffic is seen in Preston, to reduce disruption as much as possible. Roads will remain open on weekdays and Saturdays.

"These important investigations will ensure works can be carried out on time and with minimal disruption once the construction phase of the Student Centre commences, currently scheduled for early 2019"

“As this preparatory work will impact on traffic coming into the City centre, we would advise road users to allow more time when travelling on Sundays.

“These important investigations will ensure works can be carried out on time and with minimal disruption once the construction phase of the Student Centre commences, currently scheduled for early 2019.

“The teams involved are doing everything possible to ensure this essential work is completed quickly to minimise any inconvenience.”

The project, which is part of the University’s £200 million Masterplan development, will also see improvements made to hard and soft landscaping throughout the Adelphi Quarter. As part of the preparatory work, trees on the Adelphi roundabout will be removed and the University has pledged to add to the area’s existing stock in great numbers during the course of the development.

UCLan’s new Student Centre, which has targeted a BREEAM (environmental quality) rating of ‘excellent’, will be 7,304 sqm providing a new reception area, informal learning spaces and a student wellbeing support centre.

Designed as an iconic gateway to the City, the new square will span 8,440 sqm providing flexible and adaptable spaces for a wide range of community, public, business and student uses.

Any questions about the preparatory investigations being carried out can be sent to UCLanMasterPlan@uclan.ac.uk